The reconstruction with technical re-equipment of Demidovsk Central District Hospital boiler house with replacement of outdated boilers with modern ones with an installed capacity of 630 kW on solid fuel (wood processing waste)

The working project provides for the installation of a boiler house with an installed heat capacity of 630 kW for the heat supply of the demidovskaya Demidovsk Central District Hospital. The boiler house will use wood processing waste as solid fuel.
The boiler house is connected to existing networks and engineering support systems in accordance with the technical conditions of Demidovsk Central District Hospital.

Summary technical and economic indicators of the project


n/a

Indicator

Remark

Title

Unit of measure

Numerical value

1

Building area

m2

185,3

 

2

Structural volume

m3

968,3

 

3

Total area

m2

174,2

 

4

Installed heat capacity

kW

630

 

Gcal/hour

0,542

 

5

Heating capacity of the boiler room

 

 

 

5.1

hour

kW

630

 

Gcal/hour

0,542

 

t/hour

27,09

Heat carrier at dt=20 deg

5.2

annual

ths.MJ

4931,7

When the operating mode is set

Gcal

1177,9

6

Fuel consumption

 

 

 

6.1

natural

 

 

Fuel – wood waste

6.1.1

hour

kg

193,5

6.1.2

annual

т

420,7

6.2

conditional

 

 

 

6.2.1

hour

t. u. p.

96,7

 

6.2.2

annual

t. u. p.

210,34

 

7

Specific consumption of conventional fuel

kg.u. p/Gcal

178,76

 

8

Installed capacity of electric consumers in the boiler house

kW

5

 

9

The consumption of electric energy

 

 

 

9.1

sentry

kW*h

3,5

 

9.2

annual

ths.kW*h

16,0

 

10

Specific consumption of electric energy

kW*h/Gcal

13,6

 

11

Water consumption for own needs

m3

6,16

Annual Kw=0,5

11.1

Specific water consumption

m3/Gcal

1,0

 

12

Estimated amount of capital investment in the project volume, total

ths.UAH

249,943

 

12.1

including the cost of the CMR

ths.UAH

51,465

 

12.2

including the cost of equipment and furniture and inventory

ths.UAH

148,463

 

12.3

including the cost of other work and expenses

ths.UAH

50,105

Including VAT

13

Estimated labor intensity of the CMR

ths.person*hour

1,132

 

14

Standard duration of the CMR

months

2,5

 

15

Annual operating costs

thousand UAH

421,929

Calculated

16

Cost of heat energy

UAH/Gcal

358,21

Calculated


План

План 2

Генеральный план. Транспорт

епловая схема. Экспликация оборудования

ЗАКЛЮЧЕНИЯ

Plan 1 Plan 2
General plan. Transport Thermal scheme. Equipment explication CONCLUSIONS